Commercial

Kapolei Business Center

Project Details

Location Kapolei, HI
Project Size 62,000 SF
Product Type Class A Office
Year 2024
Status Completed

About This Project

Project Timeline

1

Preconstruction & Design

3 months

Site surveys, permitting, architectural design, value engineering

2

Site Work & Foundations

2 months

Grading, utilities, concrete foundations, structural steel

3

Shell & Core

6 months

Structural framing, building envelope, MEP rough-in

4

Interior Buildout

4 months

Tenant improvements, finishes, systems commissioning

5

Closeout & Occupancy

1 month

Final inspections, punch list, certificate of occupancy

Budget Breakdown

Site Work & Foundations 15%
Structural & Shell 30%
MEP Systems 25%
Interior Finishes 20%
Solar & Sustainability 10%

Cost Distribution

This breakdown represents the approximate distribution of project costs across major categories. Warrior Construction provides detailed cost estimates during preconstruction to help clients understand where their investment is going.

Site Work & Foundations Structural & Shell MEP Systems Interior Finishes Solar & Sustainability

Challenges & Solutions

Coordinated logistics for importing specialized curtain wall materials to Hawai'i while maintaining schedule

Engineered foundation design for volcanic soil conditions unique to the Kapolei region

Achieved LEED certification through integrated sustainable design and construction practices

Managed 30+ subcontractor partners across overlapping work phases without schedule delays