Downtown Office Modernization
Project Details
About This Project
Project Timeline
Design & Procurement
4 weeksSpace planning, finish selections, long-lead ordering
Demolition & MEP Rough-in
4 weeksCubicle removal, new electrical, data cabling
Buildout & Finishes
6 weeksGlass partitions, flooring, ceiling, cafu00e9 buildout
Technology & Commissioning
2 weeksAV installation, IT testing, furniture, occupancy
Budget Breakdown
Cost Distribution
This breakdown represents the approximate distribution of project costs across major categories. Warrior Construction provides detailed cost estimates during preconstruction to help clients understand where their investment is going.
Challenges & Solutions
Before & After