Commercial Retail

Walmart Kapolei Entrance & Structural Remodel

Project Details

Location Kapolei, Oʻahu
Project Size 3 new door openings
Year 2026
Status Under Construction

About This Project

Warrior Construction LLC (license BC-34373) is completing a structural remodel scope at a Walmart retail location on Farrington Highway in Kapolei, Hawai‘i, performing the self-perform demolition, concrete, masonry, carpentry, drywall/metal framing, and painting package as a subcontractor on a broader store renovation. The work centers on cutting three new door openings into the existing building envelope: a new exterior door with an accompanying concrete entry stoop, a new interior door, and a new interior access door serving the store’s Beauty Sales department.

Opening a new exterior door through a fully grouted 8-inch CMU wall on an occupied, operating retail building requires careful sequencing. Warrior’s crews saw-cut and demolish the existing concrete slab and sidewalk at each new opening, build temporary dust containment walls to isolate active retail areas during construction, and install steel jamb columns, lintels, and plates at the new openings. New reinforcement is doweled into the existing grouted CMU with adhesive anchors, with masonry patched and restored to match adjacent construction.

Because the store remains open to the public throughout construction, all work in customer-facing areas is performed as night work, with the team adhering to Walmart’s and the general contractor’s safety protocols and phasing the work around store operations — reflecting Warrior’s capability to execute structural and finish work safely inside a live, big-box retail environment under a compressed nighttime schedule.

Pre-Construction Documentation

This project is in its pre-construction phase. Photos below document existing interior conditions ahead of the new door openings. More progress photos will be added as work proceeds.

Scope of Work

  • New exterior & interior door openings

Project Photos

Pre-construction interior condition photo, Walmart Kapolei door opening projectPre-construction interior condition photo, alternate angle, Walmart Kapolei

Project Timeline

1

Containment & Demolition

Sept–Oct 2026

Dust-containment walls, then saw-cut and demolition at the three new door openings. All work in customer areas is done at night.

2

Structural Steel & Masonry

Steel jamb columns and lintels, adhesive-anchored dowels into grouted CMU, and masonry patching at each opening.

3

Doors, Carpentry & Paint

Owner-furnished doors and hardware, weatherstripping and drip caps, wall patching, and epoxy or standard paint on door frames.