Walmart needed a bigger walk-in freezer and five new loading-dock pits built inside a store that never stopped serving customers.
Warrior’s crew is saw-cutting and demoing the existing slab, excavating and forming a new insulated freezer slab with vapor barrier and rebar, and rebuilding all five dock leveler pits with new formwork and reinforced concrete. Framing, Level 4 drywall, and new overhead doors close out the interior work — all of it scheduled around the store’s hours so shelves stay stocked and customers never see a disruption.
The result taking shape: an expanded freezer and five dock pits built to warehouse-grade tolerances, without costing Walmart a single day of operation.
Scope of Work
- Freezer expansion slab
- 5 new dock leveler pits