AOAO / Multi-Family

Dowsett Point Planter Waterproofing Removal

Project Details

Location Honolulu, Oʻahu
Project Size Planter box · condominium
Year 2026
Status Completed

About This Project

Dowsett Point’s planter box was holding water against the structure, and the association needed the failed waterproofing exposed and the saturated soil gone before any permanent repair could begin.

Warrior Construction removed the planter soil and the existing waterproofing down to the structural slab. Because the area collects rain quickly, we set up temporary pumps to keep standing water under control and installed a remote monitoring system with cameras and connected power controls, so water levels could be watched without a crew on site every day.

The result is a clean, dry, fully exposed substrate that the engineers and owner can inspect, ready for new waterproofing in the next phase.

Scope of Work

  • Planter soil removal
  • Existing waterproofing removal to the structural slab
  • Temporary pumping and dewatering
  • Remote camera and pump monitoring
  • Substrate left clean and ready for new waterproofing

Project Photos

Planter area with grass before soil removal at Dowsett PointPlanter box at Dowsett Point before soil removalWarrior crew removing soil from the planter deckPlanter soil removed in buckets and staged for disposalPlanter deck exposed down to the slab after soil removalStaging area during planter demolitionAerial view of the planter deck cleared of soilPlanter deck with remaining soil, gravel and protectionAerial view of the planter during soil removalAerial view of the planter with soil removal nearly completeExposed planter deck with Honolulu skylineExposed planter slab after waterproofing removalPlanter deck protected with polyethylene sheetingPoly-lined planter with dewatering pumpTemporary pump setup in the planter boxPlanter slab edge after old waterproofing was removedPlanter slab and wall base after waterproofing removalPlanter area at the stair landing with rock and debris removedPolyethylene sheeting lining the narrow planter walkway

Project Timeline

1

Proposal Finalized

Feb 13–15, 2026

Scope revised with the property team and the final proposal issued.

2

Site Documentation

Feb 24 – Mar 4, 2026

Existing planter conditions photographed and the work area set up.

3

Soil Removal

Mar 2 – Mar 24, 2026

Planter soil, gravel and irrigation lines removed in buckets and hauled out by bin. The work was more than half complete by Mar 5 and finished Mar 24.

4

Water Protection & Pumping

Mar 10 – Apr 8, 2026

Planter covered with plastic sheeting, temporary pumps set to control rainwater, and remote monitoring installed.

5

Turnover

By Apr 22, 2026

Clean, exposed substrate handed over for the next-phase waterproofing.