Commercial

Downtown Office Modernization

Project Details

Location Honolulu, HI
Project Size 28,000 SF
Product Type Office Renovation
Year 2022
Status Completed

About This Project

Project Timeline

1

Design & Procurement

4 weeks

Space planning, finish selections, long-lead ordering

2

Demolition & MEP Rough-in

4 weeks

Cubicle removal, new electrical, data cabling

3

Buildout & Finishes

6 weeks

Glass partitions, flooring, ceiling, cafu00e9 buildout

4

Technology & Commissioning

2 weeks

AV installation, IT testing, furniture, occupancy

Budget Breakdown

Demolition & Prep 10%
Construction & Finishes 35%
MEP & Technology 30%
Furniture & Equipment 15%
Design & Soft Costs 10%

Cost Distribution

This breakdown represents the approximate distribution of project costs across major categories. Warrior Construction provides detailed cost estimates during preconstruction to help clients understand where their investment is going.

Demolition & Prep Construction & Finishes MEP & Technology Furniture & Equipment Design & Soft Costs

Challenges & Solutions

Completed the fast-track renovation in just 16 weeks from demo to occupancy

Managed all work within an occupied high-rise with strict noise and delivery windows

Achieved acoustic privacy goals in an open-plan layout through strategic engineering

Integrated enterprise-grade AV and IT infrastructure within aggressive timeline constraints