Project Timeline

1

Preconstruction

2 months

Site planning, permits, value engineering

2

Site Work & Infrastructure

2 months

Grading, utilities, parking, stormwater systems

3

Building Construction

5 months

Shell construction, roofing, exterior finishes

4

Tenant Improvements

3 months

Individual tenant buildouts, landscaping, signage

Budget Breakdown

Site Work & Parking 20%
Shell Construction 30%
MEP Systems 20%
Tenant Improvements 20%
Landscaping & EV 10%

Cost Distribution

This breakdown represents the approximate distribution of project costs across major categories. Warrior Construction provides detailed cost estimates during preconstruction to help clients understand where their investment is going.

Site Work & Parking Shell Construction MEP Systems Tenant Improvements Landscaping & EV

Challenges & Solutions

Completed the project on a tight 12-month schedule despite supply chain disruptions

Designed flexible tenant spaces accommodating 1,200 to 8,000 SF configurations

Integrated heritage-inspired design elements honoring Waipahu's plantation history

Installed EV charging infrastructure and solar-ready roof for future sustainability upgrades