Waipahu Town Center
Project Details
About This Project
Project Timeline
Preconstruction
2 monthsSite planning, permits, value engineering
Site Work & Infrastructure
2 monthsGrading, utilities, parking, stormwater systems
Building Construction
5 monthsShell construction, roofing, exterior finishes
Tenant Improvements
3 monthsIndividual tenant buildouts, landscaping, signage
Budget Breakdown
Cost Distribution
This breakdown represents the approximate distribution of project costs across major categories. Warrior Construction provides detailed cost estimates during preconstruction to help clients understand where their investment is going.