Kailua Ohana Residences
Project Details
About This Project
Project Timeline
Design & Permitting
3 monthsMulti-family design, community input, permits
Foundations & Utilities
2 monthsConcrete foundations, site utilities, structural steel
Framing & Envelope
3 monthsWood framing, roofing, windows u2014 currently in progress
MEP & Finishes
3 monthsElectrical, plumbing, interior finishes, appliances
Landscaping & Closeout
1 monthNative landscaping, community garden, final inspections
Budget Breakdown
Cost Distribution
This breakdown represents the approximate distribution of project costs across major categories. Warrior Construction provides detailed cost estimates during preconstruction to help clients understand where their investment is going.