Institutional / Senior Living

Craigside Parking & Recreation Deck Structural Repair

Project Details

Location Nuʻuanu, Honolulu
Project Size Two towers · multi-phase deck
Year 2026
Status Under Construction

About This Project

Warrior Construction LLC is performing structural repairs to the recreation deck and underlying parking structure at Craigside, a senior living community in Nu‘uanu, Honolulu, under a two-tower (Towers I & II) rehabilitation program. The scope addresses long-term structural deterioration common to elevated concrete decks in Hawai‘i’s coastal climate: spalled concrete at walls, edge slabs, soffits, and top slab surfaces across multiple sequenced parking deck phases, combined with a full structural and waterproofing restoration of the recreation deck above.

Work began with ground-penetrating radar (GPR) scanning to locate post-tension tendons and anchors before any slab chipping, so repairs proceed without compromising the post-tensioned reinforcement. Crews are carrying out concrete spall repair and crack injection across the deck phases, followed by replacement of the recreation deck’s expansion joint system and a cold fluid-applied urethane waterproofing membrane. The recreation deck slope and drainage scope has been completed.

Construction is sequenced in phases to keep the community’s parking and common areas functional, with resident notices issued ahead of each phase to manage dust and access. Two parallel crews are working — one on the parking deck spall-repair sequence and one on the recreation deck’s structural, expansion-joint, and waterproofing scope — without displacing residents.

Scope of Work

  • Concrete spall repair
  • expansion joints & waterproofing

Project Photos

Craigside parking deck structural spall repair, NuʻuanuCraigside parking deck repair, phase DP-3AStructural inspection on the Craigside recreation deckCraigside parking deck repair progress

Project Timeline

1

GPR Scanning & Investigation

Aug 2026

Ground-penetrating radar locates post-tension tendons and anchors before any slab chipping.

2

Parking Deck Spall Repair

Aug 2026 onward

Concrete spall repair and crack injection across sequenced deck phases (DP-3A through DP-6).

3

Recreation Deck Slope & Drainage

Completed

Slope and drainage scope on the recreation deck is complete.

4

Expansion Joints & Waterproofing

In progress

Replace the recreation deck expansion joint system and apply the fluid-applied urethane waterproofing membrane.

5

Substantial Completion

February 2027 (contract target)

Final completion follows in late February 2027.