Commercial Retail

Walmart Hilo Storefront Modification

Project Details

Location Hilo, Hawaiʻi Island
Project Size 2 new door openings
Year 2026
Status Coming Soon

About This Project

Warrior Construction LLC is serving as the self-performing subcontractor for a storefront entrance modification at Walmart Store #2473 in Hilo, Hawai‘i, working under general contractor Tri-State General Contractors. The scope centers on two new openings in an active, fully operational retail store: a new exterior door with an accessible concrete stoop and aprons cut into an existing CMU wall, and a new interior Breakroom door. The project requires Warrior’s crews to coordinate demolition, structural masonry infill, and finish work around ongoing store operations and customer traffic on Hawai‘i Island.

The work package combines eight self-performed trade scopes — demolition, concrete, masonry repair, carpentry, store fixture relocation, door and hardware installation, drywall and metal framing, and painting — into a single accountable scope from demolition through punch-out. Crews will saw-cut and remove existing CMU to form the new exterior door opening, shore the wall during the cut, pour a new concrete footing and stoop slab with sloped aprons, and infill the opening with CMU and a bond-beam lintel.

Because the work takes place inside a live, occupied big-box store, sequencing is a key part of the plan: fixture relocation and interior finish work in customer-facing areas will be performed during off-hours night shifts, while exterior masonry and concrete work proceeds during standard daytime hours. Warrior’s crew will mobilize to the Big Island from O‘ahu for the duration of the project, reflecting the company’s capability to self-perform multi-trade commercial scopes as a single point of accountability for national retail clients across every Hawaiian island.

Scope of Work

  • New exterior door
  • concrete stoop & interior door

Project Timeline

1

Notice to Proceed

Oct 5, 2026

Crew mobilizes from Oʻahu to Hawaiʻi Island. Roughly 20 working days overall.

2

Fixture Relocation

Store gondolas and racking moved clear of the new door locations during night shifts.

3

Exterior Opening & Stoop

Shore the wall, saw-cut the CMU opening, pour the footing and stoop slab with sloped aprons, and infill with CMU and a bond-beam lintel.

4

Doors, Finishes & Punch-Out

Steel door frame, owner-furnished door, ADA hardware, the interior breakroom door, drywall patching and paint.